Skip to main content

Assistant principal injured in fall on new sidewalk; defendant says she was inattentive.

 

The Case

  • Case Name: Nora Garcia v. PCL Construction, Inc., et al.
  • Court and Case Number: Los Angeles Superior Court / 25LBCV00290
  • Date of Verdict or Judgment: Thursday, August 13, 2026
  • Date Action was Filed: Thursday, February 06, 2025
  • Type of Case: Premises Liability, Trip and Fall
  • Judge or Arbitrator(s): Hon. Michael P. Vicencia
  • Plaintiffs:
    Nora Garcia, 53, assistant principal for special education
  • Defendants:
    PCL Construction Services, Inc. (general contractor for the construction project)
  • Type of Result: Jury Verdict

The Result

  • Gross Verdict or Award: $3,773,873
  • Contributory/Comparative Negligence: PCL Construction Services, Inc. 65%; Orange Unified School District (non-party) 20%; Knowland Construction Services, Inc. (non-party) 10%; plaintiff 5%. The jury found concrete subcontractors, Jezowski & Markel and Dean Visosky Contractors, not negligent.
  • Economic Damages:

    Future medical: $150,000 

    Past lost earnings:$253,750

    Future lost earnings: $370,123 

  • Non-Economic Damages:

    $3,000,000

  • Trial or Arbitration Time: 8 days
  • Jury Deliberation Time: Parts of two days

The Attorneys

  • Attorney for the Plaintiff:

    Kramer Trial Lawyers, APC, by Daniel Kramer and Adam Manaa, Los Angeles.

  • Attorney for the Defendant:

    Wood Smith Henning & Berman LLP by Sam McDermott (Aliso Viejo) and Jade Tran (Los Angeles).

The Experts

  • Plaintiff’s Medical Expert(s):

    Jonathan Berkowitz, M.D., orthopedic surgery.

  • Defendant's Medical Expert(s):

    William Stetson, M.D., orthopedic surgery.

    James Rosenberg, M.D., psychiatry.

    Brian King, M.D., radiology.

  • Plaintiff's Technical Expert(s):

    Peter Lupo, construction safety.

    Enrique Vega, vocational rehabilitation.

  • Defendant's Technical Expert(s):

    Brian Iler, construction safety.

    Steve Molina, vocational rehabilitation.

    Elizabeth Pettit, Ph.D., human factors,

    Appaji Panchangam, Ph.D., biomechanical engineering.

Facts and Background

  • Facts and Background:

    Plaintiff, an assistant school principal, tripped and fell on an uneven concrete lip measuring approximately 5/8 inch that jutted upward from a smooth-surface sidewalk outside a newly constructed building at Orange High School in Orange.

    Defendant PCL Construction Services, Inc. was the general contractor for the construction project. Plaintiff sustained a fractured left elbow and fractured right kneecap.

  • Plaintiff's Contentions:

    That PCL knew about the concrete lip and failed to remediate it prior to plaintiff's fall.

    That at an October 2, 2024 punch-list meeting, three weeks before the fall, PCL acknowledged the concrete lip was a tripping hazard and accepted responsibility for fixing it, but did not remediate it before plaintiff fell.

  • Defendant's Contentions:

    Defendant alleged that plaintiff was inattentive, and thus, negligent. Also, that cross-defendant concrete subcontractors Jezowski & Markel and Dean Visosky Contractors were negligent, and that several non-party entities were negligent.

Injuries and Other Damages

  • Physical Injuries claimed by Plaintiff:

    Fractured left elbow and fractured right kneecap.

Subscribe Today
Access All the Case Details Behind Every Verdict

JuryVerdictAlert.com provides limited case details for public viewing so you can see the scope of our coverage. However, access to complete case summaries, full fact patterns, damages breakdowns, attorney and expert information, and advanced search features is reserved for subscribers.

To review the full version of each verdict in our database you’ll need an active subscription to JuryVerdictAlert.com.